Phase II of the Waipahu High School project features a new three-story classroom building, connected to the existing Phase I wing by covered walkways on each level. A landscaped mall with accessible walkways links the new wing to an existing building. The facility serves students in grades 9–12, offering classrooms, support areas, and utility spaces for both students and staff.
CSquare Steel designed, fabricated, and furnished all (630 linear ft.) hot-dip galvanized railings, guardrails, pipe sleeves and associated hardware for ramps, stairs, walkways, and balconies at various site locations. Erection drawings, shop drawings, and PE-stamped calculations were provided for all delegated design elements.